Operating InstructionsTurbomat TM 150/199/220 Translation of the original German operating instructions for the operatorRead and follow the instructio
2.4 Permitted usesThe Froling Turbomat TM is designed exclusively for heating domestic water. Onlyuse fuels specified in the "Permitted fuels&quo
Changing the fuel CAUTIONIncorrect parameter settings:Incorrect parameter settings have a significant adverse effect on the functioningof the boiler,
2.4.4 Protective equipment for operating staffYou must ensure that staff have the protective equipment specified by accident pre‐vention regulations.▪
▪ Danger of fire due to flammable materials. No flammable materials should be stored near the boiler. Flammable objects (e.g.clothing) must not be put
Return liftIf the hot water return is below the minimum return temperature, some of the hot wateroutfeed will be mixed in.CAUTIONRisk of dropping belo
2.6 Safety devices14562ABC33 Safety2Safety devicesOperating Instructions TM 150/199/220 | B0310611_en 15
Item Description Description1 Main switch Before starting any maintenance work: Switch off the entire system❒The power to all components is switched o
2.6.1 External safety devicesSafety cut-out switch for sliding floor hydraulic chamberBefore starting any maintenance work in the hydraulic chamber of
2.7 Residual risksWARNINGWhen touching hot surfaces:Severe burns are possible on hot surfaces and the flue gas pipe!When work is carried out on the bo
2.8 Emergency procedure2.8.1 Overheating of the systemIf the system overheats and the safety devices fail to operate, proceed as follows: NOTICE! Do n
Contents1 General 41.1 Product overview 52 Safety 72.1 Hazard levels of warnings 72.2 Pictograms used 82.3 General safety information 92.4 Permitted u
3 Operating the system3.1 Assembly and initial startupMontage, Installation und Erstinbetriebnahme des Kessels darf nur durch qualifiziertesPersonal e
3.2 Filling/refilling the store with fuelGenerell ist beim Befüllen des Lagerraumes auf die Verwendung des richtigen Brenn‐stoffes zu achten:⇨ See &qu
3.2.1 Sliding floor discharge unit❒ The maximum dumping height (depending on the fuel density) as specified in theoperating instructions for the slidi
Blowing in fuel with the stirrer arms free and residual fuel present❒ Before filling the store, shovel any residual fuel over the middle of the stirre
3.3 Heating the boiler3.3.1 Switching on the system❒ Turn the main switch on the switch cabinet to the "ON" position➥After the system check
Once the firewood is alight:❒ Use the cleaning tool to push fuel to the back of the combustion chamber Start the boiler:❒ Close the combustion chamber
3.3.6 Switching off the system WARNINGWhen switching off the main switch in automatic mode:Serious combustion faults leading to serious accidents are
4 Servicing4.1 General information on servicingRegular cleaning of the boiler extends its life and is a basic requirement for smoothoperation.You shou
WARNINGInspection and cleaning of the combustion chamber with the combustion chambertemperature sensor in positionRisk of damage to the thermocouple!
4.3 Maintenance schedule Servicing4Maintenance scheduleOperating Instructions TM 150/199/220 | B0310611_en 29
4.1 General information on servicing 274.2 Inspection and cleaning 284.3 Maintenance schedule 294.3.1 Required jobs and checks 30 Daily30 Weekly30 Mon
4.3.1 Required jobs and checks❒ The following maintenance schedule is based on max. 3000 service hours peryear.➥ Reduce the intervals if this number i
Monthly7 Combustion chamber ❒Using the flat scraper, pull the ash on the combustion chamber grate out throughthe cleaning port door❒ Carefully remove
➥ Change any worn or deformed components❒Check the grate drive for dirt and deposits9 Air-cooled grate side plates ❒Check the grate side plates for di
11 Lambda probe ❒Unscrew and remove the Lambda probe➥ CAUTION: Lambda probe may be hot!❒ Refit and finger-tighten the lambda probe➥ Check the seal aft
❒Check the grate area and ash rakes for dirt and deposits. Clean where necessary➥ Check the seal when replacing the cleaning coverSix-monthly13 Flue
15 Heat exchanger ❒Open the cover on the heat exchanger❒ Remove all dirt and deposits from the chamber❒ Check the turbulator or check the function of
❒ Check the seal when replacing the ash removal flange➥ Because of the high temperatures to which the screw is exposed, never re‐move all the ash. Alw
19 Heat exchanger cover❒ Check fibre-glass seal for perfect alignment on the door frame➥ Check the imprint on the fibre-glass seal.If the imprint of t
❒Mark the position of the flange❒ Loosen the blower flange screws ❒Take out the blower and clean the blower wheel with a brush➥ Refit in the marked
Empty the ash containerEntaschungWärmetauscherEntaschungRetorte Chamber ash removal:❒ Unscrew the wing nuts on the ash container flange❒ Separate th
1 GeneralThank you for choosing a quality product from Froling. The product features a state-of-the-art design and conforms to all currently applicabl
4.3.2 Maintenance schedule for safety devicesNo. Component / Maintenance Operation Int.1 System pressure❒Check the system pressure on the pressure gau
4.3.3 Maintenance instructions for hydraulic systemWARNINGDo not use unskilled personnel for hydraulic system maintenanceRisk of injury and damage to
4.4 Preparing to test emissions❒ According to the stipulations of Austrian standard ÖNORM M 5861-1, the flue gaspiping must have a built-in DN100 test
NOTICEInstalling non-original parts will invalidate the guarantee.❒Only replace components or parts with original replacement parts 4.7 Disposal info
5 Troubleshooting5.1 General faults in the power supplyError characteristics Cause of error Elimination of errorNothing is shown on the dis‐playNo pow
5.3 Faults with fault message If a fault has occurred and has not yet been cleared:❒Status LED flashes red❒ A fault message is shown on the display Th
6 Appendix6.1 Addresses6.1.1 Address of manufacturerFRÖLINGHeizkessel- und Behälterbau GesmbH Industriestaße 12A-4710 GrieskirchenAUSTRIA TEL 0043 (0)
1.1 Product overview634789125 1 Wood chip boiler – Froling Turbomat 150 kW or 220 kW2 Vertical 3-pass heat exchanger with Efficiency Optimisation Syst
1213141416171819202122101112 10 Switch cabinet with integrated Lambdatronic H 3000 controller11 Main switch: Switches the power supply on and off for
2 Safety2.1 Hazard levels of warningsThis documentation uses warnings with the following hazard levels to indicate directhazards and important safety
2.2 Pictograms usedThe following symbols are used in the documentation and/or on the boiler to showwhat is required and forbidden and to give warnings
2.3 General safety informationDANGERIf the device is used incorrectly:Incorrect use of the system can cause severe injury and damage.When operating th
Comments to this Manuals